Additional exercises

1. What happens if the NCS3 capacity is increased from 0.1487 Mm3/day to 0.3 Mm3/day? Try this intervention out in a new scenario cloned from the Baseline.

Implement this in a scenario and see how ther performance of the Gaborone reservoir is impacted

  1. Increase the NSC2 capacity by increasing the max_flow of the Future Pump PS4.2 node to 0.3 Mm3/day from 0.11 Mm3/day and the max_flow of the Pump PS1 node to 0.3 (see screenshots below)

How does this change impact Gaborone and Dikgatlong reservoir performance? Try this intervention out in a new scenario cloned from the Baseline.

Last updated